Roll-Off Dumpsters and Haul-Off Planning for Demolition Bids
Haul-off is where good labor numbers go to die. Here is how to count cans and loads from the takeoff, pick trucks or cans, and price every haul-off cost on its own line.
Valentino Dore
Founder, Demotek
8 min readKey takeaways
- Count cans and loads twice, once by volume and once by weight, and carry the larger number.
- Light interior debris fills cans by volume. Concrete, masonry, and dirt fill them by weight, usually long before they look full.
- Trucks beat cans on heavy, high-volume work with a loader on site. Cans beat trucks on interior, light, or sorted debris.
- Haul, disposal, rental days, overweight, permits, and loading labor are separate costs. Price each as its own line.
- Get the hauler's terms in writing: included tons, rental days, prohibited items, and trip charges.
Why haul-off gets underbid
Haul-off sits at the end of the estimate, after the interesting work of measuring and pricing the demolition itself. By the time an estimator gets there, it is tempting to write down a number of cans from feel and move on. That is how a job with a good labor number still loses money: the cans fill faster than planned, half of them come back overweight, and the disposal invoice is twice the line in the bid.
This guide walks through planning haul-off the same way you plan the rest of the job: from quantities, with every assumption written down and every cost on its own line.
Step 1: Get the debris quantity in tons and loose yards
Everything starts with how much debris the job makes. From the takeoff, convert each material to two numbers:
- Tons, from the in-place volume times the unit weight.
- Loose cubic yards, from the in-place volume times a swell factor, or from your history of loose yards per demolished square foot on similar work.
Keep materials separate where they will be separated on site: concrete, masonry, metals, wood, and mixed debris. The debris weight table has typical tons per cubic yard and swell factors to start from.
Step 2: Pick the can size by material
Roll-off containers are sold by volume. Common sizes are 10, 15, 20, 30, and 40 cubic yards, though what is available depends on the hauler. The right size depends on what goes in it:
- Small cans (10 to 15 CY) for heavy material such as concrete, brick, block, and dirt. Many haulers limit heavy material to smaller cans because a large can full of concrete would exceed what the truck can legally carry.
- Mid-size cans (20 CY) for mixed debris and general demolition, where weight and volume both matter.
- Large cans (30 to 40 CY) for light, bulky debris: drywall, framing, ceilings, carpet, insulation, and interior finishes.
Step 3: Count the hauls by volume and by weight
For each material, compute the number of hauls two ways:
- By volume: loose CY divided by the usable volume of the can. Cans are rarely loaded perfectly full and level, so use the fill you actually see on your jobs rather than the nameplate volume.
- By weight: tons divided by the weight limit or included tonnage for that can.
Carry the larger of the two. For drywall and framing it is almost always the volume count. For concrete and masonry it is almost always the weight count. Mixed debris can go either way, which is exactly why you check both.
If you plan to go over the included tonnage on purpose, because paying overage is cheaper than an extra haul, put the expected overage tons in the bid as their own line.
Step 4: Decide between trucks and cans
Roll-off cans are not the only way to move debris. On larger jobs, dump trucks loaded directly by an excavator or loader are often cheaper and faster. Use this as a starting rule:
- Trucks when the material is heavy, the volume is high, a loading machine is already on site, there is room for trucks to queue and turn, and the facility is close enough for several turns a day.
- Cans when the work is interior, the debris is light, it comes out by hand or by cart, the site has no room for truck traffic, the job runs for weeks at a slow pace, or you need separate containers to sort materials for recycling.
Many jobs use both: cans for the interior strip-out phase, trucks for the structure and the slab. Price each phase with the method that fits it.
Step 5: Work out truck cycle time
If you are trucking, the number of trucks comes from the cycle time, not the debris volume alone. A cycle is load, haul to the facility, wait and dump, and return. Estimate each part:
- Load time, which depends on the loading machine and the material.
- Travel time both ways, at realistic speeds for the route and the time of day.
- Facility time, including the scale and the line to dump. Ask the facility when it is busiest.
Loads per truck per day is the working day divided by the cycle. The number of trucks is the number of loads the demolition produces each day divided by loads per truck. Matching the two keeps the machine from waiting on trucks and the trucks from waiting on the machine. The crew sizing guide covers the same balance from the crew side.
Step 6: Choose the disposal facility
The facility matters as much as the container. Concrete recyclers, metal yards, transfer stations, construction and demolition landfills, and municipal solid waste landfills accept different materials at different rates, and the closest one is not always the cheapest once you add the trucking. Sorting a material out of the mixed stream can turn a disposal cost into a lower rate or a credit. The disposal routing guide goes through how to compare facilities, and the salvage credits guide covers scrap and reuse.
Step 7: Price haul-off as separate line items
A single “dumpsters” line hides too much. When the job runs over, you will want to know which part ran over. Break haul-off into:
- Haul charges. Number of hauls by can size, or truck hours or loads.
- Disposal. Tons by material at the rate for the facility it goes to.
- Overweight. Expected tons above the included tonnage.
- Rental. Days beyond the included rental period, for each can on site.
- Permits. Street or right-of-way permits if a can sits on a public street.
- Loading labor and equipment. The time to get debris from where it is demolished into the can or truck, including carts, chutes, and elevator time.
- Site protection. Plywood or plates under cans to protect paving, and cleanup of the can area.
- Credits. Scrap metal and recycled material credits, shown as their own negative lines.
Read the hauler’s terms before you bid
Haulers price differently, and the differences are in the fine print. Before relying on a quote, confirm:
- What tonnage is included in each haul, and the overage rate.
- How many rental days are included, and the daily rate after.
- Trip or dry-run charges when the driver cannot reach or swap the can.
- Relocation charges for moving a can on site.
- Prohibited items, such as tires, batteries, appliances with refrigerant, paint, liquids, and anything hazardous, and the fees if they are found.
- Contamination fees on cans meant for a single material.
- Fuel or environmental surcharges added to the invoice.
Then write your assumptions into the bid: number of hauls, tons per haul, and disposal facility. If the owner or GC changes the disposal route or adds material, you have a basis for the change.
Site logistics that change the count
- Placement. A roll-off truck needs a long, straight approach and overhead clearance to drop and pick up a can.
- Swap timing. If the hauler can only swap once a day, you may need a second can on site so the crew is never waiting.
- Building access. On upper floors, the limit is usually the elevator or the chute, not the can.
- Neighbors and hours. Restricted delivery hours reduce how many swaps or truck turns you get in a day.
How Demotek handles haul-off
Haul-off goes wrong when it is a separate guess instead of a result of the takeoff. In Demotek it is a result:
- Debris by weight and volume. Each scope assembly carries its debris forward as tons and loose cubic yards, by material.
- Loads from both. The disposal step takes the weight and the volume and gives back the loads and the tons, so you never count cans by one number alone.
- Your own dump sites. Recyclers, transfer stations, and landfills are set up once with their rates, per ton or per yard, and each material goes to the right one.
- Separate lines. Haul and tipping land as their own line items, so when a job runs over you can see which part did.
The bid sheet can also show the price per export ton or per export cubic yard, which is the number to sanity-check on a job that is mostly hauling.