Demolition Bid Checklist: Exclusions and Clarifications That Protect Your Margin
The qualifications page decides who pays when the building turns out different from the drawings. Here is a checklist of the exclusions and clarifications that matter most.
Valentino Dore
Founder, Demotek
7 min readKey takeaways
- An exclusion says what is not in the price. A clarification says how you read the scope. An assumption says what you relied on. Use all three, on purpose.
- Write exclusions for this job, in plain language. A page of generic boilerplate is easy to ignore and hard to enforce.
- The biggest margin risks in demolition are hidden: hazardous materials, buried utilities, unknown structure, and below-grade conditions.
- Attach a unit price to every quantity you could not verify, so a surprise becomes a change order instead of a loss.
- Run the same checklist on every bid, and add to it every time a job teaches you something.
Why the qualifications page protects your margin
Demolition is the trade most exposed to what nobody can see at bid time. Walls hide asbestos, slabs hide utilities, ceilings hide old structure, and the drawings for a building that is coming down are often the oldest and least accurate drawings on the job. Your price can only cover what you knew when you wrote it.
The qualifications section of the bid is where you say what that was. It does not win the job by itself, but on the jobs you win, it decides who pays when the building turns out to be different from the drawings. A clear one turns surprises into change orders. A vague one turns them into arguments you usually lose.
Exclusions, clarifications, and assumptions
Use three kinds of statements, and keep them distinct:
- Exclusions remove work from your price. “Excludes abatement of hazardous materials.”
- Clarifications say how you read an unclear scope. “Slab removal is limited to the area hatched on D-101.”
- Assumptions state the conditions your price relies on. “Price assumes a 6 inch slab with wire mesh. Add a unit price per inch for thicker slab.”
Assumptions are the most underused of the three. They do not refuse work, which makes them easier for a GC to accept, and they give you a clean basis for a change when the condition turns out to be different.
1. Scope limits
- Demolition limits are as shown on the listed sheets and revisions.
- List the drawings, addenda, and specification sections the price is based on, by number and date.
- Items marked “existing to remain” are protected in place, and the price does not include restoring items damaged by others.
- “Remove and salvage” and “remove and reinstall” items: who stores them, where, and whether reinstall is included.
- Depth of foundation removal, and whether piles are cut off or extracted.
- Whether the slab, the vapor barrier, and the subbase come out.
- Whether backfill, compaction, and grading are included, and to what standard.
2. Hazardous materials
- Abatement of asbestos, lead, PCBs, mold, and other regulated materials is excluded unless listed as included.
- The price assumes a hazardous materials survey has been done and abatement is complete before demolition starts.
- Removal of universal waste such as fluorescent lamps, ballasts, mercury devices, and batteries: included or excluded, and by whom.
- Refrigerant recovery from equipment, and removal of tanks and their contents.
- Contaminated soil, and any testing or disposal of it.
- What happens if suspect material is found during demolition: work stops in that area, and the schedule and cost adjust.
If your company does abatement too, keep it as a separate price with its own qualifications. The abatement and demolition sequencing guide covers why.
3. Utilities
- Disconnection and capping of utilities by the owner or the utility company, before demolition starts.
- Locating private underground utilities is by others, unless included.
- Work around live utilities that must stay in service, and any temporary utilities needed to keep a building running.
- Removal of abandoned underground utilities, and how far beyond the building line.
4. Structure and engineering
- Engineering surveys, demolition engineering, and shoring design are included or by others.
- Temporary shoring or bracing of structures to remain, adjacent buildings, and party walls.
- The price assumes existing structure is as shown. Concealed structure, added slabs, or encased steel are extra.
- Post-tensioned concrete is excluded or priced separately.
- Pre-construction surveys of neighboring buildings, vibration monitoring, and crack monitoring.
5. Site, access, and working hours
- Working hours the price assumes, and whether night, weekend, or holiday work is included.
- Access the price assumes: elevator use, loading dock, laydown area, and truck access.
- Whether the building is vacant or occupied during the work, and any protection the occupancy requires.
- Traffic control, flaggers, street closures, and their permits.
- Site fencing, security, and who provides them.
- Temporary power, water, and sanitation: by others or included.
6. Schedule
- Duration and crew size the price is based on, and number of mobilizations.
- Additional mobilizations, phasing, or work out of sequence are extra.
- Delays from others, such as abatement running late or utilities not disconnected, adjust schedule and cost.
- Weather assumptions for exterior work.
7. Disposal and salvage
- Debris becomes the property of the contractor unless items are listed for the owner.
- Salvage and scrap credits are included in the price, or excluded, and which items.
- Disposal destination and recycling or diversion requirements, including any documentation the project needs.
- Disposal of owner-left contents, furniture, and stored material.
The salvage credits guide covers how to carry credits without betting the margin on them.
8. Protection, dust, and restoration
- Dust partitions, negative air, and floor protection included or excluded.
- Dust control water source and runoff control on exterior work.
- Patching, painting, and finishing of surfaces exposed by demolition are excluded.
- Repair of paving, landscaping, and curbs damaged by required access is excluded unless included.
- Final cleaning: broom clean, or a higher standard.
9. Permits, fees, and requirements
- Demolition permit, and who pays for it.
- Notifications to air quality or environmental agencies.
- Prevailing wage, certified payroll, and any local hiring or workforce requirements. The prevailing wage guide covers how these change the price.
- Bonds, and what they are priced at.
- Insurance limits beyond your standard coverage, and additional insured requirements.
10. Commercial terms
- How long the price is valid.
- Payment terms and retainage the price assumes.
- Escalation for labor, fuel, or disposal rates on long or delayed jobs.
- Whether the price is a lump sum, unit price, or time and material, and which unit prices apply to changes.
Unit prices for what you cannot verify
Some quantities cannot be confirmed before the work starts. For each one, attach a unit price and state the quantity you carried:
- Additional slab thickness, per inch per square foot.
- Additional concrete or footings, per cubic yard.
- Unforeseen underground tanks or structures, per item or per hour.
- Extra disposal, per ton by material.
- Additional crew time, per hour by classification.
A unit price with a stated base quantity turns an unknown into arithmetic. Without it, the same discovery becomes a negotiation you start from behind.
How to make the checklist stick
A checklist only helps if it runs on every bid. Keep a master list, and for each new job, go line by line and decide include, exclude, clarify, or not applicable. Delete what does not apply. A short list written for this job is read. A long list copied from the last one is not.
Then close the loop. After every job that cost more than planned, ask whether a line on this list would have covered it, and add it if not. Over time the list becomes a record of every lesson your shop has paid for. For the mistakes that most often lead there, see common demolition estimating mistakes.
How Demotek handles exclusions and clarifications
In Demotek, the proposal is written from the estimate itself, so the scope and exclusions it lists match what you actually priced. Pulling a cost out of the bid is a toggle on the bid sheet, and the proposal follows it.
- Alternates for what you cannot verify. Save a variant of the bid, for example with and without foundations, and quote it as an alternate. It prints in the proposal priced as the difference from the base bid.
- Bond and markup in one place. Overhead, profit, and bond sit on the bid sheet, so the price you qualify is the price you send.
- Sent from your own email. With Gmail or Outlook linked, the proposal goes out from your address, lands in your Sent folder, and replies come back to you.
- Addenda you do not miss. Project mail files bid emails onto the right project and turns invitations to bid into projects with a tap, so the drawings and addenda you list in your qualifications are the ones you were actually sent.