Prevailing Wage and Certified Payroll in Demolition Bids
On prevailing wage work the building comes down the same way, but every hour costs more and every week needs paperwork. Here is how to build a labor price that holds up.
Valentino Dore
Founder, Demotek
9 min readKey takeaways
- On prevailing wage work, the wage determination sets the minimum base rate and fringe for each classification. Your bid starts there, not at your shop rates.
- Classification is the biggest pricing decision. Hours spent running a machine are paid at the operator rate, whoever is in the seat.
- Fringe can be paid into bona fide plans, in cash, or both. How you pay it changes your burden, so price it the way your payroll actually runs.
- Certified payroll is real work every week. Carry the admin time as its own line.
- Time records by worker, by classification, by day are the foundation. If the field hours are wrong, the certified payroll is wrong.
What changes on a prevailing wage job
Public demolition work, and a lot of privately developed work with public money in it, comes with prevailing wage requirements. The scope is the same: the building still comes down and the debris still gets hauled. What changes is the minimum you must pay each worker, how you document it, and how much office time the job consumes.
For an estimator, the danger is pricing a prevailing wage job with the same labor rates as private work and finding out at the first payroll that every hour costs more than the bid carried. This guide covers what to look for in the bid documents and how to build the labor price so it holds up.
Which rules apply
There are two broad families of prevailing wage requirements:
- Federal. The Davis-Bacon Act and its Related Acts cover construction, alteration, and repair contracts on federal and many federally assisted projects. Covered contracts include the applicable wage determination and labor standards clauses in the bid documents.
- State and local. Many states and some cities have their own prevailing wage laws for public works, with their own thresholds, wage schedules, registration rules, and reporting systems. Some require contractors to register before they can bid or work on public projects.
A single job can carry both: a state public works project with federal funding may have a federal wage determination and a state schedule, and you generally pay the higher rate for each classification. Demolition adds one more wrinkle. Whether a standalone demolition contract is treated as construction under Davis-Bacon can depend on whether construction is planned at the site afterward, so if the documents are unclear, ask the agency before you price.
Step 1: Find the wage determination
The wage determination is the schedule of minimum rates for the job. For federal work it is identified by number and modification in the bid documents, and general wage determinations are published on SAM.gov by state, county, and type of construction: building, heavy, highway, or residential. State schedules are usually published by the state labor department.
Before you price, confirm:
- The determination number and modification the job uses, and whether a newer modification has been published since the bid documents were issued.
- The type of construction, since the same county can have very different rates for building and heavy work.
- Whether a state or local schedule also applies.
Step 2: Map your crew to classifications
A wage determination lists rates by classification, such as laborer, operator, truck driver, and sometimes demolition-specific laborer groups. Your crew does not get paid by job title. Each worker is paid the rate for the work they actually perform.
- Operators. Hours on an excavator, skid steer, or loader are paid at the rate for that equipment group. If a laborer runs the skid steer for two hours, those two hours are operator hours.
- Laborers. Check whether the schedule has separate groups for different laborer tasks, and which group covers demolition work.
- Drivers. Truck drivers may be covered for time on the site, with different rules for hauling off it. Read the determination and ask if unsure.
- Missing classifications. If the work needs a classification that is not listed, federal rules have a process to request one through the contracting agency. Do not guess a rate.
Split classification is allowed when a worker does more than one kind of work, but only with accurate daily records of the hours spent in each. Without those records, the safe assumption is the higher rate for all of them. The crew sizing guide covers how to build the crew itself.
Step 3: Price base rate plus fringe, then burden
Each classification has a base hourly rate and a fringe benefit rate. The total is the minimum hourly package. How you meet the fringe changes your cost:
- Into bona fide plans. Health, pension, and similar contributions count toward the fringe requirement.
- In cash. Any fringe not covered by plan contributions is paid to the worker as additional wages, which generally means payroll taxes apply to it as well.
- A mix. If your plan cost per hour is lower than the required fringe, the difference is paid in cash.
Then add your burden on top: payroll taxes, workers’ compensation, liability insurance, and anything else your burdened rate normally carries. Which of these apply to the base only and which to the cash fringe depends on your state, your carrier, and your payroll setup. Use the actual numbers from your accounting rather than a percentage carried over from private work.
Step 4: Price overtime and schedule rules
Federal construction contracts above the threshold set by the Contract Work Hours and Safety Standards Act require overtime at one and a half times the basic rate for hours over 40 in a work week. Some state laws and some schedules add daily overtime or premium rates for nights, weekends, and holidays.
If the job requires night or weekend work, or the schedule only works with long weeks, price the overtime explicitly. It is easy to carry overtime hours at straight time by habit.
Step 5: Account for apprentices
Apprentices may be paid less than the journeyworker rate only if they are registered in an approved apprenticeship program, and only within the ratio that program allows. A worker who is not registered, or who exceeds the ratio, must be paid the full rate. Some public agencies also set apprenticeship hour goals or requirements. If you plan to use apprentices to keep labor costs down, confirm they qualify before you price them.
Step 6: Price the compliance work
Prevailing wage jobs add office and field work that private jobs do not have. Price it as its own line, by hours:
- Certified payroll. Weekly payroll reports for every worker on the job, with a signed statement of compliance. Federal work commonly uses the WH-347 form or an equivalent format, and some states require electronic submission through their own systems.
- Subcontractor payrolls. If you are the prime, you are responsible for collecting and reviewing your subcontractors’ payrolls, including your trucking company if its drivers are covered.
- Postings. The wage determination and the required notices must be posted where workers can see them.
- Interviews and audits. Agencies may interview workers and review records during the job. Someone has to prepare for that.
- Other programs. Local hire, workforce, and participation requirements often come with their own reporting.
Agencies can withhold payment when payrolls are late or wrong, so the cost of slow paperwork is cash flow as well as hours.
Step 7: Write the qualifications
Put your wage assumptions in the bid, so a change in the rules is a change in the price:
- The wage determination number and modification you priced.
- The classifications you priced the work under.
- The working hours and overtime the price assumes.
- Whether certified payroll for lower-tier subcontractors is included.
- Escalation for multi-year jobs, if later wage periods apply.
The demolition bid checklist covers the rest of the qualifications page.
Why it all comes down to time records
Every certified payroll is built from the field hours: who worked, which days, how many hours, and under which classification. If the foreman writes a crew total on a whiteboard and the office reconstructs it on Monday, the payroll is a guess signed under penalty of law.
Good time records on prevailing wage work capture, for each worker, each day:
- Start and end time, and breaks.
- Hours by classification, when a worker does more than one kind of work.
- The job, so hours on public work stay separate from private work.
- The worker’s own confirmation that the hours are right.
Those same records close the loop on the estimate: hours by classification against what the bid carried. The demolition estimating guide covers how actuals feed better rates on the next bid.
How Demotek handles prevailing wage
In Demotek, a wage class holds the base rate, the fringe, and your burden, and the loaded estimating rates for straight time, overtime, and double time on each shift. You can add wage classes that belong to a single project, so the prevailing rates for one public job sit beside your standard rates without replacing them.
Crews in the estimate are priced from those classes, so a crew template with an operator and four laborers picks up the right rate for each seat. On the job, each person on the roster can carry a pay class for that project, andfield time tracking records hours by worker and role, confirmed by the worker, ready to export for payroll.
Your certified payroll still goes through your payroll process, but it starts from hours you can trust instead of a Monday-morning reconstruction.