Reading Demolition Drawings: D-Sheets, Keynotes, Hatches, and Scope Notes
Demolition scope is spread across the whole set and written in legends, hatches, and keynotes. Here is how to read a demo set so nothing is discovered during the job.
Valentino Dore
Founder, Demotek
8 min readKey takeaways
- Demolition scope is spread across the set: demo plans, ceiling and roof plans, MEP demo sheets, structural notes, the site plan, and the specs.
- Read the legend on every sheet first. Line types, hatches, and keynote symbols mean what that sheet says they mean.
- Keynotes are scope. Each one is a line, an area, or a count, and the same number can mean different things on different sheets.
- General demolition notes add work that is never drawn. Price them like any other scope.
- AI takeoff speeds up the mechanical reading, sorting sheets, reading scale, counting tags, and tracing hatches, but the estimator still decides what each mark means.
Why demolition drawings are hard to read
New-construction drawings show what will be built. Demolition drawings show what is there now, what stays, and what goes, often on the same sheet, using line types and hatches that differ from one architect to the next. The base drawing is frequently an old survey or a scan of the original set, and the demo information is layered on top of it.
That makes the reading itself a skill. Estimators who read a demo set well find the scope that is easy to miss, and estimators who do not are the ones who discover it during the job. This guide walks through the set in the order worth reading it.
Step 1: Find every sheet with demolition on it
Start with the sheet index, and assume demolition scope lives on more sheets than the ones with “demolition” in the title. Common places:
- Demolition plans. Often numbered with a D or AD prefix, such as D-101 or AD101, though conventions vary by firm.
- Reflected ceiling demolition plans. Ceilings, grid, lights, diffusers, and soffits to remove.
- Roof demolition plans. Roofing, insulation, curbs, and rooftop equipment.
- MEP demolition sheets. Mechanical, electrical, and plumbing removals, often on their own discipline sheets with their own prefixes.
- Structural sheets. New openings in slabs and walls, shoring notes, and sequencing requirements.
- Site and civil sheets. Pavement, curbs, utilities to abandon or remove, trees, and fencing.
- Hazardous materials sheets or surveys. Locations of asbestos, lead, and other regulated materials, which change the sequence of the demolition.
- Specifications. The demolition sections, commonly in Division 02, define standards, salvage, disposal, and protection.
On a large set, finding these pages is half the morning. Tools with sheet detection read each page’s number and title and organize the upload, so the demolition pages are easy to pull out of a few hundred sheets.
Step 2: Read the legend before the plan
Every demo sheet should have a legend, and it is the key to the whole sheet. Common conventions, which you should never assume without checking:
- Dashed lines often show items to be removed.
- Solid lines often show existing construction to remain.
- Hatches mark areas of removal: flooring, slab, ceiling, roofing, or wall finishes, each with its own pattern.
- Keynote symbols, usually a number in a hexagon, circle, or diamond, point to a numbered list of demolition notes.
- Limit of work lines bound the area the scope applies to.
Step 3: Check the scale on every sheet
Before measuring anything, confirm the scale. Demo sets mix full-floor plans, enlarged plans, and details at different scales, and scanned or reprinted sheets may no longer match their title block. Measure a known dimension on each sheet to confirm. The auto-scale page explains how automatic scale detection catches mismatched pages.
Step 4: Treat every keynote as a quantity
Keynotes are where most demolition scope is actually written. Each keynote tag on the plan points to a note such as “remove existing partition to underside of deck,” “remove ceiling and grid,” or “remove and salvage door, frame, and hardware for reuse.” Each one becomes a quantity:
- A line when the note applies to a wall, a run of pipe, a curb, or a sawcut.
- An area when it applies to flooring, ceiling, slab, or roofing.
- A count when it applies to doors, fixtures, equipment, or openings.
Read the full text of each keynote, not just the first words. “To underside of deck” and “to ceiling” are different heights. “Remove and salvage” means careful removal and storage, not demolition. “Remove and reinstall” adds work after the demo is done. And check each sheet’s keynote list separately, because note 7 on the floor plan and note 7 on the ceiling plan are often different notes.
Counting tags by hand is slow and easy to get wrong on a dense sheet. With auto-count, you point at one tag or symbol and every match on the page comes back highlighted for you to verify.
Step 5: Take off each hatch as its own scope
Each hatch pattern on a demo plan is its own kind of removal, and it should be its own takeoff. Carpet removal and VCT removal price differently. Slab removal and topping removal price very differently. Keeping one takeoff per hatch type means each area lands on the right line of the estimate.
Watch for:
- Overlapping hatches, where flooring and slab both come out of the same area. That is two scopes, not one.
- Small hatched areas in corridors, closets, and restrooms that are easy to skip.
- Hatches that run under walls to remain, which may need hand work at the edges.
The demolition takeoff walkthrough covers the mechanics of tracing areas, subtracting openings, and naming each takeoff.
Step 6: Read the general demolition notes
Most demo sheets carry a block of general notes, and they are scope even though nothing is drawn. Typical examples:
- Remove all abandoned cabling, conduit, and devices in the area of work.
- Remove all existing finishes within the limit of work.
- Protect existing construction to remain, and repair any damage.
- Coordinate utility shutdowns with the owner.
- Items not shown but required to complete the work are part of the scope.
Notes like the last one are broad by design. Read them, price what you reasonably can, and clarify the rest in the bid. The demolition bid checklist covers how to word those clarifications.
Step 7: Compare demo against new work
Some demolition only shows up on the new-work drawings. A new door in an existing wall, a new opening in a slab, or a new duct through an existing shaft wall all need demolition that the demo plan may not show. Lay the new floor plan over the demo plan and look for:
- New openings in walls and slabs that are shown as existing to remain.
- Walls on the demo plan that are still present on the new plan, or the reverse.
- Structural sheets that call for openings, pockets, or removals.
- Finish schedules that call for new flooring where the demo plan shows no flooring removal.
Where the two disagree, send a question before the bid and state your assumption in the qualifications.
Selective and structural sets read differently
On a selective interior job the drawings carry most of the detail, and the work is reading many small keynotes and hatches carefully. On a full structural takedown the drawings are often thinner, and more of the scope comes from the specification, the site plan, and the site walk. The selective vs structural guide explains how the estimate changes between the two.
How Demotek reads a demo set
Most of the time spent reading a demo set is mechanical: finding the right sheets, confirming the scale, counting tags, and tracing hatches. That is the part AI takeoff is built for:
- Step 1, finding sheets.Sheet detection reads each page’s number and title and organizes the upload.
- Step 3, scale. Auto-scalereads the scale of each sheet and catches mismatched pages.
- Step 4, keynotes.Auto-count finds every instance of a tag or symbol you point at.
- Step 5, hatches. The takeoff engine proposes areas and lengths traced from the drawing.
Nothing goes into the bid until you confirm it. The judgment, what each keynote means, where the scope ends, what the general notes add, stays with the estimator. Once confirmed, each quantity feeds a scope assembly that prices it, and theAI takeoff for demolitionarticle explains why propose-and-confirm is the right model.