Structural Demolition Pricing: The Bid Breakdown

Structural demolition pricing is equipment-driven. Here is the bid breakdown - equipment days, production rates, disposal routing, salvage credits, shoring, and the preconstruction scope that turns a tight bid into a winning one.

11 min read

Key takeaways

  • Structural demolition pricing is dominated by equipment days, not labor hours. Get the equipment mix right and the rest follows.
  • Production rates are measured in tons-per-day or floors-per-day rather than SF, and they swing wildly with building height and material mix.
  • Disposal cost is the biggest single line item. Concrete to the crusher, steel to the scrap yard, the rest to hardfill or landfill - get the routing right and salvage credits offset the cost meaningfully.
  • Shoring is its own engineering scope. If the takedown sequence needs temporary support, it gets its own line item with its own price.
  • Permits, abatement, and utility disconnect are real preconstruction line items. Bids that bury them in overhead miss the number.

What structural demolition actually involves

Structural demolition is the removal of load-bearing elements - walls that hold up floors, slabs, columns, foundations, or the entire building. The work is equipment-heavy: 30- to 80-ton excavators with shears, pulverizers, and breakers, sometimes cranes for top-down sequencing on tall structures, dust suppression systems, and water trucks. The crew is smaller than an interior demo - a foreman, an operator or two, a couple of laborers - but the equipment day-rate is many times higher.

For a side-by-side with interior work, see Selective vs Structural Demolition. This piece is specifically about how to price a structural takedown.

Equipment is the line item that drives everything

On a typical full-building takedown, equipment costs are 35–55% of the bid. The equipment days drive the labor days (operators), the consumables (shear cutting edges, breaker chisels), and the schedule (which drives general conditions and mobilization). Pricing the equipment wrong cascades into every other line item.

The right way to price equipment is:

  1. Pick the equipment mix - a primary high-reach for the takedown, a secondary excavator for material handling, a skid steer for site cleanup, dump trucks for haul-off.
  2. Estimate production in tons per machine-day for the primary equipment. A 50-ton high-reach with a shear runs 200–400 tons per day on a steel-framed mid-rise; a smaller class runs less.
  3. Compute machine-days - total tons divided by tons per machine-day, with a buffer for weather and mobilization downtime.
  4. Price each machine-day at the burdened rental rate plus fuel, consumables (shear edges, breaker tools), and operator hours.

Production rates that matter

Rough envelopes - your foreman's actual numbers will be tighter:

  • Single-story commercial slab removal (6" with rebar): 1,500– 3,000 SF per machine-day with a hydraulic breaker and excavator.
  • Steel-framed mid-rise (3–6 stories) takedown: 150–300 tons per machine-day with a high-reach + shear.
  • Concrete-framed mid-rise: 80–180 tons per machine-day - slower because reinforcement makes the shear work harder.
  • Industrial structures (process plants, refineries): highly variable - anywhere from 50 to 250 tons per machine-day depending on congestion and material mix.
  • Foundation removal (slab + footings + walls): 60–120 cubic yards per machine-day.

Disposal is the other half of the bid

On a structural takedown, disposal is typically 20–30% of the total price. The material mix is dominated by concrete (going to the crusher) and steel (going to the scrap yard), with a smaller share of hardfill and landfill. The routing math decides whether disposal is a manageable cost or a runaway one.

The five-destination model:

  • Concrete crusher for slab and structural concrete. Cheap tipping, often returns as recycled aggregate. Salvage credit is small but tipping is favorable.
  • Scrap yard for steel, rebar, copper, brass. Buyback - this is where salvage credits live, and on a steel-heavy structural job they can offset a meaningful share of disposal cost.
  • Hardfill for clean inert debris - broken brick, block, clean concrete chunks. Cheap tipping, usually short haul.
  • Asphalt recycler if the job has paving demolition. Often free or paid.
  • Landfill for the residual mix. Expensive - minimize.

Full routing model in Disposal Routing in Demolition Bids.

Shoring is its own line item

If the structural sequence requires temporary support - partial-floor removal with occupied floors above, partial-wall demolition with structure remaining, top-down takedown with sequenced floor loading - shoring is its own engineering scope and its own bid line item. Shoring design comes from a structural engineer, the material is rented falsework or fabricated steel, and installation is its own crew-day count.

Bids that don't break out shoring are either burying it in equipment days (underbidding) or missing it entirely (much worse). It is the single most common preconstruction surprise on a structural job.

Preconstruction line items

Before a single excavator rolls, the bid covers preconstruction scope:

  • Permits - demolition, dust, asbestos, sometimes road-closure. Municipal fees and the labor to file.
  • Abatement - asbestos, lead paint, PCBs in light ballasts. This is usually subbed out to a licensed abatement contractor; treat it as a separate scope on the bid.
  • Utility disconnect - electric, gas, water, telecom. Each utility has its own request process and timeline; coordination is the cost more than the utility's invoice.
  • Site protection - fencing, signage, pedestrian protection where relevant, sometimes overhead protection on adjacent buildings.
  • Pre-demolition documentation - adjacent-building condition survey, vibration monitoring program, dust monitoring plan.

What modern estimating tooling changes

For structural demolition specifically:

  • Equipment-day-based circuits - your structural assemblies price the equipment first, then the labor and consumables that follow. Same math the foreman does in his head, encoded so every estimator hits it.
  • Disposal routing with cycle-time math - the tool computes haul cycles from the job site to each of your disposal destinations and prices the trucks accordingly. Salvage credits are first-class line items.
  • Preconstruction line-item templates - permits, abatement sub-bid, utility disconnect, fencing. The template makes sure each one gets priced on every structural bid.

Book a 30-minute walkthrough with a structural job you've bid recently - we'll run the numbers side-by-side.

Wire up your first bid

Ready to bidsmarter?

See Demotek in action - a 30-minute walkthrough with our team, tailored to the way your crew bids work. No commitment, no pressure.

Demotek logo

DEMOTEK

Modern takeoff and estimating built for demolition contractors. Bid faster, win more, and run your team off one source of truth.

Operational